In data centre construction, delays in start-up, rather than physical damage to the works, are emerging as the defining risk for Construction All Risks insurers. This trend is already evident in emerging loss experience, where project delays account for a significant proportion of the overall claim. Critical electrical, cooling and IT infrastructure is highly specialised in data centres. Replacements of these components are constrained by long lead times, supply chain disruption and limited commissioning expertise. Consequently, even relatively modest physical damage can trigger cascading delays across the construction chain, materially extending the path to practical completion. Mitigating factors include early procurement of critical equipment, strategic spares, supplier diversification and robust project scheduling to reduce recovery times following a loss.